04/17/2012 Project meeting
- Deliverable: Improve simulation stability for deep penetrations and clamping of impulses.
04/10/2012 Project meeting
04/03/2012 Project meeting
03/20/2012 Project meeting
- Deliverable: Research Bullet and Havok SDKs. Compile and experiment with code demos.
03/13/2012 Project meeting
- Deliverable: Research existing open-source physics engines.
- Deliverable: Adjustable viewpoint in OpenGL environment.
02/28/2012 Project meeting
- Deliverable: Research existing open-source physics engines.
- Deliverable: Adjustable viewpoint in OpenGL environment.
02/28/2012 Third Project meeting
Deliverable: Spinning Box using OpenGL and SDL.
02/14/2012 Second Project meeting
- Deliverable: Set up SDL-based OpenGL development environment. (Past Due)
- Deliverable: Getting glowing cube done. (Due 2/21/12)
- Deliverable: Complete reading list. (Due 2/21/12)
02/07/2012 First Project meeting
- Given site access.
- Discussed project deliverables.
- Deliverable: Get blog, bio, schedule, detailed deliverables on site. (Due 2/13/12)
- Deliverable: Set up SDL-based OpenGL development environment. (Due 2/13/12)
- Deliverable: Render static scene. (Due 2/13/12)
|